One of the UK’s biggest energy consumers, Ineos Chlor has improved energy
efficiency by almost a fi fth over the past decade, writes Hugh Constable
Ineos Chlor is the only producer of chlor-alkali
and chlorinated derivatives in the UK, and it owns
and operates the UK’s largest chlor-alkali facility
at Runcorn in Cheshire. The Runcorn site is one
of the largest energy consumers in the country,
with an annual electricity consumption in excess
of 250MW – roughly equivalent to that of the
city of Liverpool. The company’s electricity bill
represents approximately 70% of the variable cost
of production of chlorine.
Over the past decade, however, Ineos Chlor’s
energy consumption per tonne of product has
fallen by nearly 18% (Figure 1), yielding huge
savings in CO2 emissions. If the company’s 2008
product basket had been produced in 1998, CO2
emissions would have been 1270kt. Actual CO2
emissions from the site in 2008 were 1017kt – a
saving of 253kt.
This year, the company has begun construction
of what will become the largest Energy from
Waste CHP (combined heat and power) plant in
the country. Located adjacent to Runcorn site,
the plant will eventually burn 750,000t of Solid
Recovered Fuel (SRF), derived from municipal waste
treatment facilities within Greater Manchester
and in the North West. Ultimately, the plant will
produce 70MW of electricity and 50MW of steam,
which equates to 25% of the Runcorn site’s total
energy needs. Nationally, the project will save an
estimated 500,000 t/year of carbon-equivalent
emissions.*
Runcorn site’s commitment to reducing
its energy consumption and improving the
sustainability of its operations began more than
a decade ago, when the site was originally under
the ownership of ICI. With the arrival of Climate
Change Agreements (CCAs) in 1999, energy
effi ciency gained even greater prominence, and
the company’s Energy Efficiency Improvement
Programme was launched in spring 1999. An
Energy Efficiency Steering Committee was set
up, containing representatives from all site
operating sections, and including a full-time
energy manager.
During the first few years the committee met
monthly in order to establish energy efficiency
improvement (EEI) as important for senior
management. The long-term objective, however,
was to engrain EEI as part of the day-to-day
management of the site.
The committee assessed the potential for
improvement in each operating section over
the period to 1999/2010 and compiled a list of
potential projects, and this was used to develop
targets for each section. These were consolidated
into a target that became the company’s CCA
target: a 7% improvement in energy efficiency by
2010 relative to 1998. This goal was made even
harder, however, by the fact that most of the site’s
energy is consumed by the electrolysis process
to produce chlorine, which offered little scope
for improvement without a complete technology
overhaul. Instead, our efforts were therefore
directed at the non-electrolytic operations, which
would therefore need to see a 15% improvement
to achieve our overall target.
The company implemented the ‘no cost/low
cost’ projects immediately since these gave a fast
payback and could generally be funded from revenue
rather than capital budgets. It also introduced
positive discrimination in favour of all energy saving
projects, meaning that these had lower investment
hurdles than other cost reduction opportunities.
Late in 1999, Runcorn site agreed the first ever
‘Partnership for Energy Efficiency’ with the Energy
Efficiency Best Practice Programme (EEBPP),
then run by the Energy Technology Support Unit
(ETSU); this has since been replaced by the Carbon
Management Programme operated by the Carbon
Trust. Under this partnership, the EEBPP provided
funding for detailed audits on two of our plants
and our largest cooling tower. The EEBPP also
funded consultants who provided on-site training
for our engineers and operations personnel. Three
separate seminars were held, on motors and drives,
no cost/low cost measures and refrigeration, with
audiences approaching 140.
There are well in excess of 2000 electric motors
on Runcorn site. Following the EEBPP motors
seminar, a new Motor Systems Management
(MSM) programme was implemented. Previously,
a faulty motor would simply be sent away for
refurbishment, but under the new policy the
default action would be to review the duty, and
then install a new, correctly sized, high-efficiency
motor. This meant that improvements could be
funded from revenue rather than capital budgets.
This programme has had three benefits:
- Systematic review of motor duties has resulted in
the elimination of many over-sized motors;
- Systematic review provides an opportunity to
assess whether there is a case for a variable speed
drive; and
- Eventually, the whole fleet will be replaced with
high efficiency motors.
Early in the life of the EEI Programme, the
steering committee recognised the need to identify
where energy was actually being consumed and to
actively manage that consumption. Some £2.2m
was spent on new metering and a data acquisition
system to monitor utilities consumption by each
of the plants on the site. All consumption data
are now fed automatically into a management
information system (MIS) where they can be seen
by anyone in the company. Most importantly,
plant managers have instant access to real-time
data relating to their energy usage.
Consumption data are imported into a
spreadsheet where monthly site-wide balances
of natural gas, steam and electricity consumption
are maintained. The spreadsheet also contains
production volume data for all products, so it is
possible to calculate specific consumption of each
utility by each plant. The spreadsheet calculates
actual CO2 emissions on a monthly basis and
compares this against target. The difference
between the two is a site Key Performance Indicator
(KPI) that is monitored by senior management.
This metering system, combined with the
implementation of the ‘no-cost/low cost’ projects,
resulted in a 3.4% reduction in the site’s total
specific energy consumption – equivalent to
savings in the order of 43,000 t/year of CO2, which
continues to be delivered year-on-year.
In common with other chemical majors, ICI’s
strategy in the late 1990s was to focus on higher
value, low volume chemicals, and to exit from
bulk chemicals manufacture. However, Ineos has a
different view, believing that money can be made
from large volume chemicals – provided you get your
production volumes up and your cost base down.
In just over 11 years, Ineos has grown to become
the largest private company in the UK and the third
largest petrochemicals company in the world. Most
of this growth has involved acquiring businesses
that were not wanted by their former owners.
Ineos Chlor acquired ICI’s chlor-alkali business
and Runcorn site in early 2001. The company
immediately set in motion two major asset
replacement projects and a site-wide process
automation project. All of these were aimed at
reducing variable costs, and almost by definition,
this meant improving energy efficiency.
The business invested more than £200m
in new chlorine cellrooms employing state-of-the-
art membrane technology. These cellrooms,
commissioned in 2006, deliver primary energy
savings of 12% compared with older mercury
technology, and at nameplate output the CO2
saving is about 85,000 t/year. Another £40m was
spent on a new boiler house, replacing an old and
inefficient power station.
Between 2002 and 2006, approximately
£16m was spent on a new centralised control
room at Runcorn and on a new pan-site process
automation system. The use of networked ‘smart
devices’ has enabled energy efficiency and other
process improvements to be made in ways that
were never envisaged at the start. It is believed
that approximately 18,000 t/year of CO2 savings
can be attributed to this system.
All of these measures have contributed to
a significant improvement in energy efficiency
across the site as a whole. Analysis shows that,
compared with the original ICI target of 7%,
energy consumption per tonne of product fell by
17.9% between 1998 and 2008.
Unfortunately, the law of diminishing returns
makes it increasingly hard to find financially
viable energy efficiency projects within the site,
and making further reductions in carbon footprint
requires changes in how the energy is generated.
Looking to the future, the company has now
commenced construction of what will become the
largest Energy from Waste CHP plant in the UK. This
will displace 25% of the site’s energy imports, and
reduce national CO2 emissions by 500,000 t/year.*
Hugh Constable is regulatory affairs manager at
Ineos Chlor, based in Runcorn, Cheshire, UK.
*Although because carbon accounting rules are still
under development, it is unclear exactly how much of
this will be attributable to the site.